Deep Well Dewatering - Paull TBM Reception Shaft
- Client: Skanska
- Location: Paull, Hull
- Duration: June 2018 – February 2020
Dewatering of chalk for the construction of a tunnel boring machine reception shaft beneath the River Humber
Project Overview
The National Grid needed to establish a new gas pipeline beneath the River Humber by constructing a 5-kilometre-long segmental tunnel to house the steel high-pressure gas pipe. Stuart Wells established two separate aquifer dewatering systems to dewater the superficial deposits and to depressurise the chalk aquifer and mitigate risk of potential for uplift during excavation. 4no x 22m deep wells were installed internally together with 5no x 42m external chalk wells at ~12m centres around the external perimeter of the shaft.
Objective
Stuart Wells was contracted to design a system to dewater the Paull shaft to allow a base slab tobe installed. This would ensure the stability and dryness of the shaft to receive the tunnel boring machine.
Solution
Pumping tests on-site suggested a poor connection between the Chalk and the overlying superficial deposits requiring two separate dewatering systems. Remote monitoring of groundwater levels and abstracted flow recorded data and acted as an alarm system in the event of pump failure.
Scope of Works
It was initially thought that by dewatering the lower chalk aquifer it would underdrain and have a beneficial effect on groundwater in the overlaying deposits. However, pumping tests undertaken on site suggested poor connection between the chalk and the overlying superficial deposits. Therefore, separate aquifer dewatering systems were established to both dewater the superficial deposits (Glacial Till) using 4no x 22m deep wells were drilled at ~12m centres around the internal perimeter of the cofferdam; and to depressurise the Chalk aquifer and mitigate risk of potential for uplift when excavating through the superficial deposits by pumping from 5no x 42m external deep wells.
Remote monitoring of groundwater levels and abstracted flow was set up to both record data and act as an alarm system in the event of pump failure.
Downloadable PDF
Deep Well Dewatering - Paull TBM Shaft
Related Case Studies
- Deep Well Dewatering - Ashby Folville Manor
- Basement Extension
- Ejector Dewatering - Hook WwTW
- Ejector Dewatering - Islington Pumping Station
- Deep Well Dewatering - Shaft Llanberis WwTW
- Deep Well Dewatering - Mersey Gateway Bridge
- Deep Well Dewatering - Unity Square
- Deep Well Dewatering - Glass Factory
- Wellpoint Dewatering - Laing O’Rourke
- Wellpoint Dewatering - Epworth STW
- Wellpoint Dewatering - Great Wakering Housing
- Wellpoint Dewatering – Northern Gateway
- Wellpoint Dewatering – Savill Court
- Pressure Relief Wells - EDF Hinkley Point C
- Pressure Relief Wells - UCLH Proton Unit
- Pressure Relief Wells - Werrington Grade Separation